Werk #2223: Allow cancelling actions to be omitted if the cancelled event is not (yet) open

Component Event Console
Title Allow cancelling actions to be omitted if the cancelled event is not (yet) open
Date Apr 23, 2015
Checkmk Edition Checkmk Raw (CRE)
Checkmk Version 1.2.7i1
Level Trivial Change
Class New Feature
Compatibility Compatible - no manual interaction needed

If you have an Event Console rule that uses delaying or counting at the same time as cancelling, and if this rule furthermore defines actions when cancelling, then you can have these actions only be executed if the event has made it in to the open phase. The default is still the old behaviour: that cancelling actions are also executed when the event is still being delayed or in phase counting

To the list of all Werks